The Kingston Cycleway
The Kingston Cycleway may not be one of the most talked about construction projects in Canberra, but it will make a major difference to one of the city’s busiest routes.
The shared path between Kings Avenue Bridge and Bowen Park carries people walking, riding and scooting between the city and Kingston. It was far too narrow for the amount of traffic it was handling, making it difficult for pedestrians and cyclists to use together.
The first stage of the Kingston Cycleway has addressed the worst of this bottleneck. A lane of Bowen Drive has been converted into a protected two-way cycle lane, leaving the original lakeside path for pedestrians. Later stages will extend the route through Kingston and eventually towards the Monaro Highway and Canberra Avenue underpass.
The current C2 cycling route is loosely defined and runs through the Kingston Foreshore. This new route will provide a faster and more direct connection into the city for commuters living in Kingston.
The stages
- Stage 1 - completed in 2024: The protected cycle lane between Kings Avenue Bridge and the Bowen Drive car park is complete and open. It was built by converting one vehicle lane into a cycle lane.
- Stage 2A - construction starts in August 2026: A three-metre-wide path will continue along Bowen Drive to the Wentworth Avenue and Eastlake Parade intersection. It will include improved lighting, a raised crossing and new kerb ramps. Construction is expected to be completed by the end of the year.
- Stage 2B: The route will continue along Wentworth Avenue from Eastlake Parade to Cunningham Street. Construction procurement is expected to begin in late 2026.
- Stage 2C: This section will connect Cunningham Street with the Canberra Avenue service road. The design is complete, but a construction date has not been announced.
- Stage 3: The final section will continue from the Canberra Avenue service road to the Monaro Highway and Canberra Avenue underpass. The design is complete, but this stage is currently funded for design only.
Current work
Construction on Stage 2A is expected to begin in the week starting 3 August and take around four months, with cyclists expected to be able to use the path by the end of 2026. The new path will be built along the northern verge of Bowen Drive.
Stage 2A will require 37 trees to be removed. These will be replaced at a ratio of two new trees for every tree removed, with planting planned along Wentworth Avenue and Canberra Avenue.
Access to the Bowen Drive car park may change during construction, but On-Lake Cafe will remain open.
The details
Stage 1 of the cycleway cost just under $170,000. By making use of the existing road and a recycled rubber separation kerb, it created separate space for cyclists and pedestrians without requiring an entirely new path to be built. It was completed in just a couple of months.
The later stages are more complex. Design work for Stages 2 and 3 was delayed in 2025 due to site complexities.
The Australian and ACT governments have allocated $2.7 million to the second stage of the Kingston Cycleway.
What’s missing
While the Kingston Cycleway fixes some major gaps and bottlenecks in Canberra’s cycle network, cycling south of the lake and around the National Triangle remains overly complex. Raised kerbs and a lack of dedicated cycle lanes around the offices in Barton make the final part of many commutes difficult once riders leave the main path. Some offices can only be reached by cycling on the road.
Could similar pop-up infrastructure to Stage 1 of this project be used elsewhere in the National Triangle?